How long does it usually take before I will be granted the Planning Permission?

It depends on which type of application is involved:

  • Applications involving the household and other minor planning applications – within 8 weeks.
  • For large or controversial structures and developments – within 13 weeks.
  • If the application involves developments that affect the environment – it will be subject to an Environmental Impact Assessment and is usually decided upon within 16 weeks.